Tuesday, January 10, 2012
Where did 2011 go?
Monday, May 31, 2010
Marylands First BioMag Project is a Resounding Success
Since February the demonstration project has performed extremely well. Plant performance was as follows:
Influent
BOD 250mg/L
TSS 120 mg/L
TKN 40 mg/L
TP 2.0 mg/L
Effluent
BOD <2.0 mg/L
TSS <2.0 mg/L
TN <2.0 mg/L
TP <0.1 mg/L
The plant has performed so well that the State of Maryland is considering this technology as a replacement for denitrification filters throughout the State. Not only does BioMag allow for a significant improvement in quality of effluent but the quantity of influent treated is increased substantially which makes it very attractive to budget strapped owners. Keep in mind that this project has no filters following the secondary clarifier. This performance is very typical of a BioMag project as demonstrated already in Sturbridge, MA in 2008 and Upper Gwynedd Township, PA in 2009.
Cambridge Water Technologies has two full scale BioMag facilities under construction in Sturbridge, MA and Allenstown, NH. Both facilities will be upgraded to BioMag and will be on line sometime in 2011.
This picture on the left is of Steve Woodard , inventor of BioMag and employee of CWT, A Maryland Department of the Environment (MDDOE) employee, and yours truly. This picture was taken during a tour of the BioMag equipment after a presentation of data to MDDOE, engineers and the owner of the Cascade, MD facility.
Its worth mentioning that this Maryland project would not have been such a success without the help of the staff at the Winebrenner WWTF. Mike the CPO and operators, Mark, Robin and Ryan performed like they have been working with activated sludge their entire life. Fact is, Winebrenner has RBC's for biological treatment and the combined total of activated sludge experience between the four of them was less than 5 years. So a huge thank you goes to them for plowing snow, shoveling snow and performing about 7,000 grab tests during this trial.
Thursday, February 11, 2010
2010 Project Update
I began two pilot projects with Cambridge Water Technologies (CWT) at the end of 2009. One project was located in Mystic, CT and was considered a success by the owner and their consulting engineer. This project ended in January 2010 and is currently moving towards full design.
The other CWT project is located in MD. This project continues to challenge everyone involved. We have a basic 4 stage Bardenpho process treating a side stream flow. This side stream flow is very weak due to inflow and is very cold with temperatures averaging 7 degrees celcius in January. Project goals include meeting a TN limit of 3 ppm with traditional loadings. The project continues to move ahead and I will provide an update in the near future.
CWT is growing rapidly and I hope to work closely with them in MD, TX and FL in 2010. I might even hire some employees by the end of the year.
Thursday, August 13, 2009
Shelton CT Operations Assistance
- Recycle loads from the sludge thickening process were overloading the plant with BOD and TN
- Odors associated with sludge handling were creating a nuisance in the neighborhood and needed to be controlled
- Numerous issues related to the SBR operation were identified including air flow meters that were not reading correctly, clogged decant valves from accumulated debris, and poor biomass quality related to widely fluctuating F:M.
- Consumable costs related to supplemental bacteria, polymer use and enzymes were becoming a burden for the WPCA
As a result of the initial findings, the highest priority item was to get the sludge thickening operation under control. The waste sludge holding tank was typically operated at over half full and without the ability to aerate the tank, anaerobic conditions were created which impacted sludge thickening efficiency, odors and filtrate quality. The sludge holding tank was emptied and now the staff keeps the tank empty daily. This significantly reduced the BOD and TN loading on the SBR's and allowed the staff to eliminate one of four SBR's from operation. Odors have also been reduced significantly.
It was apparent the SBR's had accumulated large amounts of debris (screening) as a result of the headworks barscreen being out of service for several months. The WPCA funded the cleaning of the SBR's which is now in progress. When the first of four SBR's were cleaned, twelve out of fifty decant valves were fouled with hair and rags. This contributed to the poor performance of the SBR's . Once the SBR was emptied, the decant valves were cleaned, all mechanical equipment was inspected and tightened and the SBR placed back on line. The remaining three SBR's will be cleaned over the next month and the plant will continue in three SBR mode going forward.
As a result of these changes to the operation of the plant it is expected the WPCA will save significant dollars on power, consumables and avoid paying nitrogen fees to the State. Once I have some firm figures, I will post the anticipated cost savings.
Wednesday, June 17, 2009
Membrane Replacement Project Successful
Here, Steve puts the finishing touches on the new membranes just prior to testing. Thanks to the Applied Water Team of Aram, Steve and Roger for their work on this project. Thanks also go out to the owners representatives Donna and Don!
Wednesday, June 3, 2009
BioMag Pilot Plant Facility
The goal of the pilot was to prove that BioMag would allow the existing 6 MGD facility to treat sustained wet weather flows of up to 12 MGD while maintaining permit compliance particularly with regards to suspended solids capture in the secondary clarifiers.
The pilot was constructed by Interstate Water and Wastewater Specialists in three weeks and officially kicked off on March 18, 2009. The plant was separated into a control section and BioMag section in essence creating the potential for each side to treat 6 MGD for a total plant flow of 12 MGD. During the first month both sides treated similar flows while the system was charged with magnetite.
Once the magnetite to biosolids ratio reached a desired level, several high flow tests were conducted for 8 hr periods culminating with a 24 hour test all greater than 6 MGD. Total suspended solids averaged less than 10 ppm and the sludge blanket was maintained less than 3 feet during the testing. Cambridge Water Technologies, EERM (Environmental Engineer and Management Associates - owners consultant) and the owner were excited about the results and all parties are considering it a success. The final report will be published in the very near future.
I have the opportunity to meet some great folks on this job. Thanks go to Lee Honeywell and his staff for making my stay in Upper Gwynedd a pleasure. Also thanks to Ed Gillette and his staff for setting the bar high enough to make me sweat!
Next on the BioMag Pilot world tour are several possible eastern US cities and towns. Stay tuned......
Welcome to the Great Blue Heron Blog
This blog is designed to give water and wastewater industry professionals an idea of some of the more interesting technologies and challenges our company faces on a day to day level.
We also hope to educate and inform our clients, partners and website visitors of some of the new advancements we are providing, as well as ways to work with older, established systems to make them more efficient.
We look forward to your comments and feedback!
- Roy